TopHat

Kitchener Barracks, Chatham

Historic barracks retained in significant modular home development

Project Overview

TopHat were the UK’s leader in technology-driven modular housing manufacturing. Using Modern Methods of Construction (MMC), they combined computer-controlled off-site manufacturing with advanced planning, design technology and innovative materials – building homes in a factory in Derbyshire before installing them on site. The ambition was to change the way residential development works: faster, cleaner, and more precise than traditional build.

The site at Kitchener Barracks tells a more complicated story. A former Royal Engineers barracks in Chatham, Kent – steeply sloping, historically significant, and tightly constrained – this was not a straightforward canvas for a modular scheme. Extensive level changes across the 4.8-acre brownfield site meant significant civil engineering and infrastructure work before a single module could arrive from the factory. The masterplan also retained historic barracks buildings at the heart of the development, requiring new modular homes to be coordinated carefully around locally significant structures.

Matrix Consult were appointed to manage the on-site delivery and provide Cost Consultancy throughout – bridging the gap between factory production and a demanding brownfield reality. Our commission covered Development Monitoring, Project Management, Employer’s Agent and Quantity Surveying across a 24-month programme, keeping the scheme on track.

^

Contract value: £4m

^

Project Duration: 24 months

^

Location: Chatham, Kent

^

Scale: Single site, Phased modular construction scheme

^

Services provided: Project Management, Employer's Agent, Quantity Surveying

Project Management

The groundworks and infrastructure had to come first – and they had to be right. On a site with significant level changes, complex drainage, and constrained access for cranage and deliveries, the preparation work was as technical as the modular installation itself. We managed that sequencing closely: coordinating civil engineering contractors, monitoring progress against the programme, and making sure the site was genuinely ready when modules began arriving on site.

Matrix Consult provided independent oversight throughout – reviewing cost, programme, procurement and risk at every stage, and giving TopHat and their funders clear, accurate reporting. We managed communications with contractors, assessed change, certified payments, and ensured the contract documentation properly reflected the performance requirements the scheme demanded: energy efficiency, durability, quality, and careful integration with the retained heritage buildings.

Modular construction brings its own pressures. Factory production schedules don’t flex easily – which means the site has to be ready when it has to be ready. We kept both sides of the process moving together, handling design refinements as they came, resolving ground-condition issues on the spot, and feeding any site-based learning back into the delivery approach. When the pressure increased, we maintained the delivery schedule.

The Outcome

The Chatham scheme delivered what modular construction at its best can achieve – and demonstrated what good project management and independent cost consultancy makes possible.

The phased modular construction development was completed within budget across a 24-month programme on a site that presented significant civil, logistical and heritage challenges. Homes were designed to use around 67% less operational energy than traditional new-build and achieve EPC ratings of B – capable of A – with a design life of at least 75 years.

Programme efficiency was maintained in line with TopHat’s wider MMC approach, delivering homes in approximately half the time of equivalent traditional construction. Matrix Consult’s independent oversight of groundworks, interfaces and cost was central to making that possible on this particular site.

Other Projects

Village Hotels

Room refurbishment, four live hotels

Hotels, Leisure

  • Project Duration: Circa 8 months (staggered start Jan 2026, due for completion early Sept 2026)
  • Location: Cheadle, Newcastle, Leeds, Wirral (multi-site, UK)
  • Scale: Multi-site
  • Services provided: Project Management, Employer's Agent, Quantity Surveying

Village Hotels

Gym and leisure refurbishment, Watford

Health and Fitness, Leisure

  • Project Duration: TBC
  • Location: Watford / Elstree
  • Scale: Single site
  • Services provided: Project Management, Employer's Agent, Contract Administration

The Padel Club

National padel rollout, Gloucester & Cheltenham

Health and Fitness, Leisure

  • Project Duration: Ongoing relationship
  • Location: UK-wide
  • Scale: Multi-site
  • Services provided: Project Management, Quantity Surveying

Fora (The Office Group)

Co-working fit-out, Great Portland Street

Commercial

  • Contract value: £2.4m
  • Project Duration: 9 Months
  • Location: Great Portland Street, Central London
  • Scale: Single site
  • Services provided: Project Management, Cost Consultancy

The Climbing Hangar

Subtitle

Health and Fitness, Leisure

  • Project Duration: Typical build 3 months per site
  • Location: UK-wide
  • Scale: Multi-site
  • Services provided: Project Management, Employer's Agent, Contract Administration

Adina Hotels (TFE)

The Hobson Cambridge and The Wellington Glasgow

Hotels

  • Project Duration: Partial programmes (acquired mid-construction, 2025)
  • Location: Cambridge & Glasgow, UK
  • Scale: Multi-site
  • Services provided: Project Management

Shelter Hall

Seafront food market fit-out, Brighton

Leisure

  • Contract value: £900,000
  • Project Duration: Delivered 2020
  • Location: Kings Road Arches, Brighton
  • Scale: Single site
  • Services provided: Project Management, Employer's Agent, Contract Administration, Quantity Surveying

PLATF9RM

Co-working fit-out, Hove Town Hall

Commercial

  • Contract value: Circa £700,000
  • Project Duration: TBC
  • Location: Hove Town Hall, Church Road, Hove
  • Scale: Single site
  • Services provided: Employer's Agent, Quantity Surveying

Oxygen Active Play

UK-wide trampoline park roll-out

Health and Fitness, Leisure

  • Contract value: £500k–£1.1m
  • Project Duration: 10–16 weeks per site
  • Location: UK-wide
  • Scale: Multi-site
  • Services provided: Project Management, Cost Consultancy

The Gym Group

Multi-gym installations, UK

Health and Fitness, Leisure

  • Contract value: £600k – £1m
  • Project Duration: 4 Months on average
  • Location: UK-wide
  • Scale: Multi-site
  • Services provided: Project Management, Contract Administration, Quantity Surveying

Matrix Consult.

Office One, 1 Coldbath Square,
Farringdon, London EC1R 5HL

info@matrix-consult.co.uk

Contact Us

If you're working on a construction project in the leisure, health and fitness, or commercial sectors, we'd love to hear from you. Tell us what you're working on, and we'll have a straightforward conversation about how we can help.

This field is required.
This field is required.
This field is required.

Matrix Consult Limited

info@matrix-consult.co.uk

Office One, 1 Coldbath Square,
Farringdon, London EC1R 5HL

Company number 05211741

© Matrix Consult 2026